This is what happens when you get a hole in your ground source heat pipes.. Sintec were back onsite this week to grout the pipes into the boreholes this involves pressure testing them first to make sure they'll work when the system is commissioned -good times. They couldn't get pressure in the last pipe which generally means theres a hole in it and they have to pull the 70m pipe out by hand and replace it -bad times